Respectfully, I think there’s a mix-up on the Hawesville numbers.
The 79 MW figure (480 MW gross power minus 401 MW critical IT load) isn’t uncontracted IT capacity.
Gross power is the total electricity available to the site. Critical IT load is the actual power that goes to